The framing layout worksheet shows a study ratio requires 1 apprentice per 6 journeypersons or fraction. How many apprentices are needed for 25 journeypersons?
Correct Answer
A) 5 apprentices.
Twenty-five divided by six is 4.17, and the fraction rounds up to 5.
Why This Is the Correct Answer
Twenty-five divided by six is 4.17, and the fraction rounds up to 5.
Why the Other Options Are Wrong
Option B: 4 apprentices.
4 apprentices. is below the supported result for apprenticeship ratio; it likely uses the wrong base, period, or account bucket.
Option C: 6 apprentices.
6 apprentices. is above the supported result for apprenticeship ratio; it likely adds an unsupported amount or compares the wrong financial base.
Option D: 25 apprentices.
25 apprentices. is above the supported result for apprenticeship ratio; it likely adds an unsupported amount or compares the wrong financial base.
Memory Technique
Apprenticeship Ratio drawer for Practicing Apprentice: label twenty-five before counting dollars.
Reference Hint
Study anchor (closed-book): memorize Apprenticeship ratio from California Labor Code Section 1777.5; DIR Division of Apprenticeship. / California Labor Code Section 1777.cited employment dutyhip ratio concepts; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
