Law & BusinessPublic Worksmedium10% of exam part

A public works claimant is owed $18,200 and later receives $5,000. What unpaid amount remains for payment-remedy analysis?

Correct Answer

B) $13,200.

The remaining unpaid amount is $18,200 - $5,000 = $13,200.

Answer Options
A
$10,560.
B
$13,200.
C
$13,300.
D
$14,200.

Why This Is the Correct Answer

The remaining unpaid amount is $18,200 - $5,000 = $13,200.

Why the Other Options Are Wrong

Option A: $10,560.

$10,560. is below the supported result for public works payment remedies; it likely omits part of the approved scope, cap, credit, or holdback.

Option C: $13,300.

$13,300. is above the supported result for public works payment remedies; it likely adds scope or money the rule does not allow.

Option D: $14,200.

$14,200. is above the supported result for public works payment remedies; it likely adds scope or money the rule does not allow.

Memory Technique

Remaining before dollars; unpaid before balance in Calculating Unpaid.

Reference Hint

Study anchor (closed-book): memorize Public works payment remedies from California Public Contract Code public works payment and retention. / California Civil Code public works stop payment notice concepts; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.