Law & BusinessPublic Worksmedium10% of exam part

Retention held is $28,000, and the agency has a good-faith dispute over $6,500. What undisputed amount should be released?

Correct Answer

D) $21,500.

The undisputed amount is $28,000 - $6,500 = $21,500.

Answer Options
A
$6,500.
B
$21,000.
C
$28,000.
D
$21,500.

Why This Is the Correct Answer

The undisputed amount is $28,000 - $6,500 = $21,500.

Why the Other Options Are Wrong

Option A: $6,500.

$6,500. is below the supported result for retention release; it likely omits part of the approved scope, cap, credit, or holdback.

Option B: $21,000.

$21,000. is below the supported result for retention release; it likely omits part of the approved scope, cap, credit, or holdback.

Option C: $28,000.

$28,000. is above the supported result for retention release; it likely adds scope or money the rule does not allow.

Memory Technique

Reconciling Public contract math: approved scope is the ruler for retention release.

Reference Hint

Study anchor (closed-book): memorize Retention release from California Public Contract Code public works payment and retention. / California Public Contract Code Section 7107; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.