A contractor is not approved to train apprentices and will employ an apprenticeable craft on a public works project. What DAS 140 step is required?
Correct Answer
D) Send DAS 140 contract award information to the committees.
DIR apprenticeship guidance says a contractor not approved to train must send DAS 140 contract award information to applicable apprenticeship committees for the craft and area.
Why This Is the Correct Answer
DIR apprenticeship guidance says a contractor not approved to train must send DAS 140 contract award information to applicable apprenticeship committees for the craft and area.
Why the Other Options Are Wrong
Option A: Send nothing unless a union asks.
Send nothing unless a union asks. skips the written authority, scope, price, notice, or release control needed for das 140.
Option B: Send DAS 140 only after final completion.
Send DAS 140 only after final completion. skips the written authority, scope, price, notice, or release control needed for das 140.
Option C: Keep the apprentice request in the project file but skip sending the required DAS notice.
Keep the apprentice request in the project file but skip sending the required DAS notice. skips the written authority, scope, price, notice, or release control needed for das 140.
Memory Technique
When dir clashes with apprenticeship, let the contract speak before Preparing Apprenticeship.
Reference Hint
Study anchor (closed-book): memorize DAS 140 from California Labor Code Section 1777.5; DIR Division of Apprenticeship. / California Labor Code Section 1777.5; DIR DAS guidance; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
People Also Study
Related Study Resources
Previous Question
A new-hire notice lists the hourly rate but omits whether the worker is paid by hour, shift, day, week, salary, piece, or commission. What required item is missing?
Next Question
A progress payment covers a specific invoice period and amount. What should related release paperwork match?