A contract price is $54,000. Approved changes add $6,750 and credits total $2,425. What adjusted contract price results?
Correct Answer
D) $58,325.
Adjusted price is $54,000 + $6,750 - $2,425 = $58,325.
Why This Is the Correct Answer
Adjusted price is $54,000 + $6,750 - $2,425 = $58,325.
Why the Other Options Are Wrong
Option A: $56,325.
$56,325. is below the supported result for adjusted contract calculation; it likely omits part of the approved scope, cap, credit, or holdback.
Option B: $57,750.
$57,750. is below the supported result for adjusted contract calculation; it likely omits part of the approved scope, cap, credit, or holdback.
Option C: $58,000.
$58,000. is below the supported result for adjusted contract calculation; it likely omits part of the approved scope, cap, credit, or holdback.
Memory Technique
Updating Summary contract math: approved scope is the ruler for adjusted contract.
Reference Hint
Study anchor (closed-book): memorize Adjusted contract calculation from CSLB 2026 Law Book; CSLB Home Improvement Contracts / Business and Professions Code Section 7159 home improvement contract requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?