A cabinet allowance is $9,500. The owner selects a package costing $10,275, with no markup on allowance overages. What adjustment is needed?
Correct Answer
C) $775 increase.
The selected package is $775 over the allowance, so the increase is $775.
Why This Is the Correct Answer
The selected package is $775 over the allowance, so the increase is $775.
Why the Other Options Are Wrong
Option A: $725 credit.
$725 credit. is below the supported result for allowance reconciliation; it likely uses the wrong base, period, or account bucket.
Option B: $750 increase.
$750 increase. is below the supported result for allowance reconciliation; it likely uses the wrong base, period, or account bucket.
Option D: $19,775 total.
$19,775 total. is above the supported result for allowance reconciliation; it likely adds an unsupported amount or compares the wrong financial base.
Memory Technique
Reconciling Cabinet money test: bucket before math for allowance reconciliation.
Reference Hint
Study anchor (closed-book): memorize Allowance reconciliation from CSLB 2026 Law Book; CSLB Home Improvement Contracts / B&P Code Section 7159 home improvement contract requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
People Also Study
Related Study Resources
Previous Question
A customer pays a $9,000 deposit before the contractor has earned the revenue. How should the deposit be classified initially?
Next Question
A subcontract requires $1,000,000 per occurrence liability coverage, but the certificate shows $500,000. How much additional per occurrence limit is needed to meet the subcontract requirement?
