A crew performs an extra before the owner signs the change order, then bills it later. What is the contract control problem?

Correct Answer

D) Approval came late.

Changed work should be authorized in writing before the work is performed.

Answer Options
A
Get written change approval.
B
Inspection record.
C
Joint check control.
D
Approval came late.

Why This Is the Correct Answer

Changed work should be authorized in writing before the work is performed.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.