A contract sets delay damages at $150 per calendar day. If an unexcused delay is 5 days, what amount is calculated?

Correct Answer

B) $750.

Five days at $150 per day equals $750.

Answer Options
A
$500.
B
$750.
C
$900.
D
$1,050.

Why This Is the Correct Answer

Five days at $150 per day equals $750.

Why the Other Options Are Wrong

Option A: $500.

$500. is below the supported result for delay charge calculation; it likely omits part of the approved scope, cap, credit, or holdback.

Option C: $900.

$900. is above the supported result for delay charge calculation; it likely adds scope or money the rule does not allow.

Option D: $1,050.

$1,050. is above the supported result for delay charge calculation; it likely adds scope or money the rule does not allow.

Memory Technique

Delay Charge gate for Checking Contract: paper opens before money moves.

Reference Hint

Study anchor (closed-book): memorize Delay charge calculation from CSLB 2026 Law Book; CSLB Home Improvement Contracts / B&P Code Section 7159 home improvement contract requirements; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.