EstatePass
Law & BusinessContractsmedium23% of exam part

After retaining 5 percent from an $18,600 progress payment, what net payment is released?

Correct Answer

A) $17,670.

The retention is $930, so the net payment is $18,600 minus $930.

Answer Options
A
$17,670.
B
$18,600.
C
$930.
D
$19,530.

Why This Is the Correct Answer

The retention is $930, so the net payment is $18,600 minus $930.

Why the Other Options Are Wrong

Option B: $18,600.

$18,600. is above the supported result for progress payment calculation; it likely adds scope or money the rule does not allow.

Option C: $930.

$930. is below the supported result for progress payment calculation; it likely omits part of the approved scope, cap, credit, or holdback.

Option D: $19,530.

$19,530. is above the supported result for progress payment calculation; it likely adds scope or money the rule does not allow.

Memory Technique

Reconciling Retention contract math: approved scope is the ruler for progress payment.

Reference Hint

Study anchor (closed-book): memorize Progress payment calculation from CSLB 2026 Law Book; California contracting practice / CSLB Law Book payment and contract administration; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.