A contract calls for 5 percent retention on an $18,600 progress payment. How much should be retained from that payment?
Correct Answer
D) $930.
Five percent of $18,600 is $930.
Why This Is the Correct Answer
Five percent of $18,600 is $930.
Why the Other Options Are Wrong
Option A: $186.
$186. is below the supported result for progress payment calculation; it likely omits part of the approved scope, cap, credit, or holdback.
Option B: $465.
$465. is below the supported result for progress payment calculation; it likely omits part of the approved scope, cap, credit, or holdback.
Option C: $900.
$900. is below the supported result for progress payment calculation; it likely omits part of the approved scope, cap, credit, or holdback.
Memory Technique
Progress Payment gate for Checking Application: paper opens before money moves.
Reference Hint
Study anchor (closed-book): memorize Progress payment calculation from CSLB 2026 Law Book; California contracting practice / CSLB Law Book payment and contract administration; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
People Also Study
Related Study Resources
Previous Question
A subcontractor qualifies its bid by saying it excludes all permit fees, but the prime contract requires the contractor to pay them. What should the prime do?
Next Question
A time-and-material change is capped at $5,000. Labor and material backup totals $5,460. What amount should be billed under the cap?
