A progress billing includes $3,700 for materials stored in the contractor's warehouse, but the contract allows billing only for work performed or materials delivered to the project. What is the best response?

Correct Answer

C) Reject or revise that billing line until it matches the contract payment terms.

Progress billing should follow the written payment terms; a charge outside the allowed delivery or work-value condition should be rejected or revised.

Answer Options
A
Approve the charge because the contractor bought the materials.
B
Hide the materials charge inside the labor line.
C
Reject or revise that billing line until it matches the contract payment terms.
D
Collect the amount as a separate cash deposit outside the contract, even though the written payment schedule says otherwise.

Why This Is the Correct Answer

Progress billing should follow the written payment terms; a charge outside the allowed delivery or work-value condition should be rejected or revised.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.