A bid tab shows one concrete quote $18,000 lower than all others because it excludes vapor barrier and reinforcing placement. What is the best estimating response?

Correct Answer

B) Normalize the scope before comparing the quote to other bids.

Quotes should be compared on equivalent scope; exclusions must be normalized before selecting a number.

Answer Options
A
Use the low number immediately because bid day is short.
B
Normalize the scope before comparing the quote to other bids.
C
Warranty card packet.
D
Assign omitted concrete scope to the owner without disclosure.

Why This Is the Correct Answer

Quotes should be compared on equivalent scope; exclusions must be normalized before selecting a number.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.