A remodel contract says work will begin 'soon' and finish 'when materials arrive.' What should be corrected before signing?
Correct Answer
D) Add the required start or approximate start timing and completion date.
CSLB home improvement guidance requires the contract to provide schedule information, including completion date, rather than vague timing.
Why This Is the Correct Answer
CSLB home improvement guidance requires the contract to provide schedule information, including completion date, rather than vague timing.
Why the Other Options Are Wrong
Option A: Delete all schedule language to avoid promises.
Delete all schedule language to avoid promises. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option B: State that the owner must guess the completion date.
State that the owner must guess the completion date. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option C: Let the field superintendent set dates after demolition, with the final date filled in only after demolition starts.
Let the field superintendent set dates after demolition, with the final date filled in only after demolition starts. skips the written authority, scope, price, notice, or release control needed for project contracts.
Memory Technique
Project Contracts square for Reviewing Residential: scope, authority, price, paper.
Reference Hint
Study anchor (closed-book): memorize Project contracts from CSLB 2026 Law Book; CSLB Home Improvement Contracts / Business and Professions Code Section 7159; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
