A scope change adds $7,800 of work and the signed change order allows 15 percent overhead and profit. What is the total change order amount?

Correct Answer

B) $8,970.

Fifteen percent of $7,800 is $1,170. Adding that to the base cost gives $8,970.

Answer Options
A
$8,580.
B
$8,970.
C
$7,915.
D
$9,750.

Why This Is the Correct Answer

Fifteen percent of $7,800 is $1,170. Adding that to the base cost gives $8,970.

Why the Other Options Are Wrong

Option A: $8,580.

$8,580. is below the supported result for project contracts; it likely omits part of the approved scope, cap, credit, or holdback.

Option C: $7,915.

$7,915. is below the supported result for project contracts; it likely omits part of the approved scope, cap, credit, or holdback.

Option D: $9,750.

$9,750. is above the supported result for project contracts; it likely adds scope or money the rule does not allow.

Memory Technique

Project Contracts gate for Checking Arithmetic: paper opens before money moves.

Reference Hint

Study anchor (closed-book): memorize Project contracts from CSLB 2026 Law Book; CSLB Home Improvement Contracts / Business and Professions Code Section 7159; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.