Before an owner hires a contractor for a remodel, which lien-prevention screening step does CSLB recommend?
Correct Answer
D) Hire licensed contractors and check the contractor's license status on CSLB's website.
CSLB mechanics lien guidance begins with choosing licensed contractors and checking the contractor's license status on CSLB's website.
Why This Is the Correct Answer
CSLB mechanics lien guidance begins with choosing licensed contractors and checking the contractor's license status on CSLB's website.
Why the Other Options Are Wrong
Option A: Select the lowest bid without checking license status.
Select the lowest bid without checking license status. skips the written authority, scope, price, notice, or release control needed for pre-contract lien prevention.
Option B: Keep the paperwork in the job file without matching it to current lien or insurance requirements.
Keep the paperwork in the job file without matching it to current lien or insurance requirements. skips the written authority, scope, price, notice, or release control needed for pre-contract lien prevention.
Option C: Check only whether the contractor has a social-media page.
Check only whether the contractor has a social-media page. skips the written authority, scope, price, notice, or release control needed for pre-contract lien prevention.
Memory Technique
Preparing Owner-Facing shortcut is not a term until paper carries it.
Reference Hint
Study anchor (closed-book): memorize Pre-contract lien prevention from CSLB Mechanics Lien guidance; CSLB license check / California Civil Code mechanics lien prevention; CSLB licensing; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?