On a $30,000 residential contract, $14,000 of work has been performed and the contractor already collected a $1,000 down payment. Ignoring retention, what is the maximum additional progress payment without exceeding the value of work performed?
Correct Answer
A) $13,000.
The total paid should not exceed the value of work performed except for the down payment. With $14,000 of work value and $1,000 already paid, the added payment is $13,000.
Why This Is the Correct Answer
The total paid should not exceed the value of work performed except for the down payment. With $14,000 of work value and $1,000 already paid, the added payment is $13,000.
Why the Other Options Are Wrong
Option B: $13,250.
$13,250. is above the supported result for project contracts; it likely adds scope or money the rule does not allow.
Option C: $10,500.
$10,500. is below the supported result for project contracts; it likely omits part of the approved scope, cap, credit, or holdback.
Option D: $6,500.
$6,500. is below the supported result for project contracts; it likely omits part of the approved scope, cap, credit, or holdback.
Memory Technique
Project Contracts cue Reconciling Homeowner'S: ceiling and percentage shake hands; the lower hand controls.
Reference Hint
Study anchor (closed-book): memorize Project contracts from CSLB 2026 Law Book; CSLB Home Improvement Contracts / Business and Professions Code Section 7159; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
