A home improvement contract uses several licensed subcontractors. Under the 2026 CSLB Law Book summary, what remains true about the prime or direct contractor?
Correct Answer
D) The prime or direct contractor remains responsible for the construction project.
The 2026 CSLB Law Book summary states that the prime or direct contractor is responsible for the construction project while not precluding discipline against subcontractors or salespersons.
Why This Is the Correct Answer
The 2026 CSLB Law Book summary states that the prime or direct contractor is responsible for the construction project while not precluding discipline against subcontractors or salespersons.
Why the Other Options Are Wrong
Option A: The prime contractor has no responsibility once subcontractors are disclosed, once the names are printed in the contract.
The prime contractor has no responsibility once subcontractors are disclosed, once the names are printed in the contract. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option B: Treat subcontractor disclosure as transferring project responsibility to each listed trade.
Treat subcontractor disclosure as transferring project responsibility to each listed trade. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option C: Tell the owner to pursue each subcontractor directly for project-wide issues.
Tell the owner to pursue each subcontractor directly for project-wide issues. skips the written authority, scope, price, notice, or release control needed for project contracts.
Memory Technique
Explaining Subcontractor shortcut is not a term until paper carries it.
Reference Hint
Study anchor (closed-book): memorize Project contracts from CSLB 2026 Law Book / Business and Professions Code Section 7159; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?