A subcontractor sends a price increase after completing added work that was never approved in the owner contract. What should the prime contractor avoid doing?
Correct Answer
D) Passing the amount to the owner as an automatic change order.
An owner change should not be treated as automatic when the written owner contract was never changed; authorization and documentation must be reviewed.
Why This Is the Correct Answer
An owner change should not be treated as automatic when the written owner contract was never changed; authorization and documentation must be reviewed.
Why the Other Options Are Wrong
Option A: Reviewing the subcontract and project records.
Reviewing the subcontract and project records. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option B: Documenting why the added work was or was not authorized, before discussing responsibility with the owner.
Documenting why the added work was or was not authorized, before discussing responsibility with the owner. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option C: Resolving responsibility under the written agreements.
Resolving responsibility under the written agreements. skips the written authority, scope, price, notice, or release control needed for project contracts.
Memory Technique
Handling Disputed shortcut is not a term until paper carries it.
Reference Hint
Study anchor (closed-book): memorize Project contracts from CSLB 2026 Law Book; California contract administration practice / CSLB Law Book contract price and change documentation; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
