A developer asks a CA Class B contractor to take a standalone framing subcontract on a multifamily project. Which classification statement is correct?
Correct Answer
C) A Class B contractor may take a prime contract or subcontract for framing or carpentry.
B&P Code Section 7057 allows a general building contractor to take a prime contract or subcontract for a framing or carpentry project.
Why This Is the Correct Answer
B&P Code Section 7057 allows a general building contractor to take a prime contract or subcontract for a framing or carpentry project.
Why the Other Options Are Wrong
Option A: The work is barred because a Class B license cannot take subcontracts.
The work is barred because a Class B license cannot take subcontracts. skips the written authority, scope, price, notice, or release control needed for class b scope in contracts.
Option B: The work is barred unless two unrelated non-carpentry trades are added.
The work is barred unless two unrelated non-carpentry trades are added. skips the written authority, scope, price, notice, or release control needed for class b scope in contracts.
Option D: The work is allowed only if fire protection work is added to the framing scope, as a way to make the job look more complex.
The work is allowed only if fire protection work is added to the framing scope, as a way to make the job look more complex. skips the written authority, scope, price, notice, or release control needed for class b scope in contracts.
Memory Technique
Deciding Whether shortcut is not a term until paper carries it.
Reference Hint
Study anchor (closed-book): memorize Class B scope in contracts from CSLB Class B classification; CSLB 2026 Law Book / Business and Professions Code Section 7057; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?