A contractor wants to verify whether a potential subcontractor's license classification is active and appropriate. What is the best tool?
Correct Answer
B) CSLB license lookup and classification information.
CSLB license lookup provides public license status and classification information useful for subcontractor screening.
Why This Is the Correct Answer
CSLB license lookup provides public license status and classification information useful for subcontractor screening.
Why the Other Options Are Wrong
Option A: A proposal listing a license number without checking current CSLB status.
A proposal listing a license number without checking current CSLB status. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for license status verification.
Option C: A verbal statement that the license covers similar jobs.
A verbal statement that the license covers similar jobs. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for license status verification.
Option D: A verbal promise from a materials supplier, even if the supplier has worked with the subcontractor before.
A verbal promise from a materials supplier, even if the supplier has worked with the subcontractor before. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for license status verification.
Memory Technique
License Status clock for Qualifying Subcontractors: party, date, proof, then rights.
Reference Hint
Study anchor (closed-book): memorize License status verification from CSLB 2026 Law Book; California Business and Professions Code; CSLB. / CSLB license check and license classification guidance; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?