A progress check has been handed to a subcontractor but has not cleared. Which release best matches the status?

Correct Answer

D) Conditional progress.

While payment has not cleared, a conditional progress release matches the payment status.

Answer Options
A
Unconditional final release.
B
Permit signoff form.
C
Certificate holder.
D
Conditional progress.

Why This Is the Correct Answer

While payment has not cleared, a conditional progress release matches the payment status.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.