A supplier first furnishes on day 1 and serves preliminary notice on day 42. Under the 20-day lookback rule, materials from what day forward are protected?
Correct Answer
B) Day 22.
A late preliminary notice protects the 20-day lookback period and later furnishing. Day 42 minus 20 days is day 22.
Why This Is the Correct Answer
A late preliminary notice protects the 20-day lookback period and later furnishing. Day 42 minus 20 days is day 22.
Why the Other Options Are Wrong
Option A: Day 1.
Day 1. is below the supported result for preliminary notice timing; it likely omits part of the approved scope, cap, credit, or holdback.
Option C: Day 42 only.
Day 42 only. is above the supported result for preliminary notice timing; it likely adds scope or money the rule does not allow.
Option D: Day 60.
Day 60. is above the supported result for preliminary notice timing; it likely adds scope or money the rule does not allow.
Memory Technique
Late before dollars; notice before balance in Entering Late.
Reference Hint
Study anchor (closed-book): memorize Preliminary notice timing from CSLB Mechanics Lien guidance; California Civil Code / California Civil Code preliminary notice 20-day lookback; mechanics lien; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?