For a direct contractor, a valid CA notice of completion can shorten the lien recording deadline to 60 days. If notice is recorded on April 10, what date is 60 days later?
Correct Answer
B) June 9.
Sixty calendar days after April 10 is June 9.
Why This Is the Correct Answer
Sixty calendar days after April 10 is June 9.
Why the Other Options Are Wrong
Option A: May 10.
May 10. is above the supported result for notice of completion; it likely adds scope or money the rule does not allow.
Option C: July 9.
July 9. is not aligned with the supported result for notice of completion; it has the wrong label or classification even if the number looks close.
Option D: April 30.
April 30. is above the supported result for notice of completion; it likely adds scope or money the rule does not allow.
Memory Technique
Calendar before dollars; days before balance in Tracking Contractor'S.
Reference Hint
Study anchor (closed-book): memorize Notice of completion from CSLB Mechanics Lien guidance; California Civil Code / California Civil Code notice of completion; direct contractor mechanics lien deadline; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?