A supplier serves preliminary notice on day 47 after first furnishing. Which period is protected by the late notice?
Correct Answer
A) Materials furnished from day 27 forward.
A late notice protects the 20-day lookback period and later furnishing. Day 47 minus 20 days is day 27.
Why This Is the Correct Answer
A late notice protects the 20-day lookback period and later furnishing. Day 47 minus 20 days is day 27.
Why the Other Options Are Wrong
Option B: All materials from day 1 forward.
All materials from day 1 forward. is below the supported result for preliminary notice timing; it likely omits part of the approved scope, cap, credit, or holdback.
Option C: No materials at all, even though a late notice can protect a lookback period.
No materials at all, even though a late notice can protect a lookback period. skips the written authority, scope, price, notice, or release control needed for preliminary notice timing.
Option D: Only materials furnished before day 20.
Only materials furnished before day 20. is below the supported result for preliminary notice timing; it likely omits part of the approved scope, cap, credit, or holdback.
Memory Technique
Estimating Lien contract math: approved scope is the ruler for preliminary.
Reference Hint
Study anchor (closed-book): memorize Preliminary notice timing from CSLB Mechanics Lien guidance; California Civil Code / California Civil Code preliminary notice 20-day lookback; mechanics lien; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?