A supplier first furnishes materials on day 1 and serves preliminary notice on day 19. What is the lien-preservation effect of that timing?
Correct Answer
D) The notice is within the 20-day period and can protect all furnished materials for that claimant.
A preliminary notice served within 20 days of first furnishing is timely for the claimant's furnished labor or materials.
Why This Is the Correct Answer
A preliminary notice served within 20 days of first furnishing is timely for the claimant's furnished labor or materials.
Why the Other Options Are Wrong
Option A: The notice is too early to matter.
The notice is too early to matter. skips the written authority, scope, price, notice, or release control needed for preliminary notice timing.
Option B: Only materials after day 19 are protected.
Only materials after day 19 are protected. is below the supported result for preliminary notice timing; it likely omits part of the approved scope, cap, credit, or holdback.
Option C: Only materials after day 20 are protected, even when the notice was actually served within the first 20 days.
Only materials after day 20 are protected, even when the notice was actually served within the first 20 days. is not aligned with the supported result for preliminary notice timing; it has the wrong label or classification even if the number looks close.
Memory Technique
Served before dollars; days before balance in Checking Whether.
Reference Hint
Study anchor (closed-book): memorize Preliminary notice timing from CSLB Mechanics Lien guidance; California Civil Code / California Civil Code preliminary notice; mechanics lien; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
