Using the same $180,000 contract and 10 percent retention, if gross earned is $90,000, what net billing is allowed before prior payments?

Correct Answer

A) $81,000.

Ten percent retention on $90,000 is $9,000, so net billing is $81,000.

Answer Options
A
$81,000.
B
$9,000.
C
$90,000.
D
$99,000.

Why This Is the Correct Answer

Ten percent retention on $90,000 is $9,000, so net billing is $81,000.

Why the Other Options Are Wrong

Option B: $9,000.

$9,000. is below the supported result for progress billing; it likely uses the wrong base, period, or account bucket.

Option C: $90,000.

$90,000. is above the supported result for progress billing; it likely adds an unsupported amount or compares the wrong financial base.

Option D: $99,000.

$99,000. is above the supported result for progress billing; it likely adds an unsupported amount or compares the wrong financial base.

Memory Technique

Progress Billing drawer for Applying Retention: label percent before counting dollars.

Reference Hint

Study anchor (closed-book): memorize Progress billing from CSLB Law and Business Study Guide; CSLB 2026 Law Book / CSLB Law and Business Study Guide Business Finances; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Law & Business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.