The finish crew seventh consecutive day in the workweek totals 8.5 hours at $36 per hour. What seventh-day pay is due?

Correct Answer

D) $468.

The first 8 hours on the seventh day are at 1.5 times and the final half hour is double time. Total pay is $468.

Answer Options
A
$306 straight.
B
$432 all overtime.
C
$486 mixed.
D
$468.

Why This Is the Correct Answer

The first 8 hours on the seventh day are at 1.5 times and the final half hour is double time. Total pay is $468.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.