A helper is called an independent contractor but uses company tools, follows company hours, and reports to a foreman. What is the risk?
Correct Answer
A) Misclassification.
A label alone does not determine worker status; control and legal classification rules can create misclassification risk.
Why This Is the Correct Answer
A label alone does not determine worker status; control and legal classification rules can create misclassification risk.
Why the Other Options Are Wrong
Option B: Wage notice.
Wage notice. misses the specific employer duty in worker classification; it does not resolve the pay, reimbursement, status, timing, or record issue.
Option C: Coverage filing.
Coverage filing. misses the specific employer duty in worker classification; it does not resolve the pay, reimbursement, status, timing, or record issue.
Option D: CSLB listed as the certificate holder.
CSLB listed as the certificate holder. misses the specific employer duty in worker classification; it does not resolve the pay, reimbursement, status, timing, or record issue.
Memory Technique
If the job needs label, the employer needs Reviewing Crew proof.
Reference Hint
Study anchor (closed-book): memorize Worker classification from California DIR/DLSE wage statement, payroll record, payday, and Wage. / California Labor Code worker classification and wage obligations; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
People Also Study
Related Study Resources
Previous Question
In the kitchen remodel file, a bid has direct labor of $22,400, materials of $18,600, and equipment rental of $4,000. If the contractor adds 18 percent markup on direct cost, what is the bid price?
Next Question
A final payment has cleared and no retainage remains. Which release status best matches the cleared final payment?