A worker is paid $23 per hour for 8 regular hours and 3 overtime hours in a day. What is the gross pay?
Correct Answer
A) $287.50.
Eight hours are paid at $23, and three overtime hours are paid at $34.50. Total pay is $287.50.
Why This Is the Correct Answer
Eight hours are paid at $23, and three overtime hours are paid at $34.50. Total pay is $287.50.
Why the Other Options Are Wrong
Option B: $253.00 straight-time.
$253.00 straight-time. is below the supported result for daily overtime calculation; it likely skips a premium-pay or employer-cost component.
Option C: $299.00 double-time.
$299.00 double-time. is above the supported result for daily overtime calculation; it likely pays the wrong premium tier or counts the same hours twice.
Option D: $345.00 all-premium.
$345.00 all-premium. is above the supported result for daily overtime calculation; it likely pays the wrong premium tier or counts the same hours twice.
Memory Technique
Daily Overtime ladder for Checking Payroll: hours climb before dollars add up Tie the cue to Daily Overtime Calculation Checking Tie the cue to Checking Payroll Finish Crew Worker.
Reference Hint
Study anchor (closed-book): memorize Daily overtime calculation from California DIR/DLSE Overtime FAQ; California Labor Code / California Labor Code Section 510 daily overtime; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?