The concrete crew worksheet shows a nonexempt worker at $18 per hour works 9 hours on the seventh consecutive day. What is the pay for that seventh day?
Correct Answer
C) $252.
On the seventh consecutive day, the first 8 hours are at 1.5 times and hours over 8 are double time.
Why This Is the Correct Answer
On the seventh consecutive day, the first 8 hours are at 1.5 times and hours over 8 are double time.
Why the Other Options Are Wrong
Option A: $162.
$162. is below the supported result for seventh consecutive day overtime; it likely skips a premium-pay or employer-cost component.
Option B: $216.
$216. is below the supported result for seventh consecutive day overtime; it likely skips a premium-pay or employer-cost component.
Option D: $324.
$324. is above the supported result for seventh consecutive day overtime; it likely pays the wrong premium tier or counts the same hours twice.
Memory Technique
Who controlled consecutive, who paid day, where is the Checking Payroll record?
Reference Hint
Study anchor (closed-book): memorize Seventh consecutive day overtime from California DIR/DLSE Overtime FAQ; California Labor Code / California Labor Code Section 510 seventh consecutive day double time; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?