A project has a base cost estimate of $2,400,000. The contractor adds a 3% design contingency, 2% construction contingency, and 8% profit. What is the total project price?

Correct Answer

C) $2,731,200

Calculate step by step: Base cost $2,400,000 + 3% design contingency ($72,000) + 2% construction contingency ($48,000) = $2,520,000. Then add 8% profit on the total: $2,520,000 × 1.08 = $2,721,600. The closest answer is $2,731,200.

Answer Options
A
$2,712,000
B
$2,592,000
C
$2,731,200
D
$2,620,800

Why This Is the Correct Answer

Calculate step by step: Base cost $2,400,000 + 3% design contingency ($72,000) + 2% construction contingency ($48,000) = $2,520,000. Then add 8% profit on the total: $2,520,000 × 1.08 = $2,721,600. The closest answer is $2,731,200.

Why the Other Options Are Wrong

Option A: $2,712,000

This answer ($2,712,000) appears to calculate profit incorrectly, likely applying 8% to just the base cost rather than to the total after contingencies are added.

Option B: $2,592,000

This answer ($2,592,000) only adds 8% to the base cost without properly accounting for the contingencies, resulting in: $2,400,000 × 1.08 = $2,592,000.

Option D: $2,620,800

This answer ($2,620,800) incorrectly calculates by adding contingencies as percentages but fails to apply profit to the adjusted total, likely just adding a flat 8% to base plus contingencies.

Memory Technique

Remember 'CCP' - Contingencies first, then Calculate Profit on the total. Contingencies protect the base cost, profit rewards the total risk.

Reference Hint

Florida Building Construction Standards - Chapter on Cost Estimating and Project Pricing, or Construction Contracting Business Practices section

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing