EstatePass
Contract AdminProceduresmedium13% of exam part

A concrete pour is scheduled for tomorrow, but the quality control checklist shows that rebar inspection has not been completed. The concrete supplier cannot reschedule without significant cost. What should the general contractor do?

Correct Answer

B) Complete the rebar inspection before proceeding with the pour

Quality control procedures must be followed in sequence. Rebar inspection must occur before concrete placement because once concrete is poured, the rebar cannot be properly inspected or corrected if deficient. The cost of rescheduling is less than the cost of potential structural problems.

Answer Options
A
Proceed with the pour and inspect the rebar later
B
Complete the rebar inspection before proceeding with the pour
C
Pour the concrete but document the deviation
D
Get written approval from the owner to proceed

Why This Is the Correct Answer

Option B is correct because quality control procedures must be followed in proper sequence, and rebar inspection is a critical step that must occur before concrete placement. Once concrete is poured, it becomes impossible to properly inspect the rebar placement, spacing, and tie connections. The structural integrity of the concrete depends on proper rebar installation, making this inspection non-negotiable. The short-term cost of rescheduling concrete delivery is minimal compared to the potential catastrophic costs of structural failure or having to demolish and rebuild defective work.

Why the Other Options Are Wrong

Option A: Proceed with the pour and inspect the rebar later

This violates fundamental quality control principles and creates serious safety risks. Once concrete hardens around the rebar, inspection becomes impossible, and any defects in rebar placement cannot be corrected without costly demolition.

Option C: Pour the concrete but document the deviation

Simply documenting a deviation does not make it acceptable. This approach still results in uninspected rebar being permanently encased in concrete, creating potential structural deficiencies that documentation cannot remedy.

Option D: Get written approval from the owner to proceed

Owner approval cannot override building code requirements and proper construction sequencing. Even with written approval, the contractor remains liable for structural defects, and the building inspector will still require proper inspections.

Memory Technique

Use the acronym 'FIRST' - Finish Inspections before Reinforcement Solidifies in Time. Always inspect rebar FIRST before concrete pours.

Reference Hint

Florida Building Code Chapter 19 (Concrete) and ACI 318 for reinforcement inspection requirements

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing