A concrete pour is scheduled for tomorrow, but the quality control checklist shows that rebar inspection has not been completed. The concrete supplier cannot reschedule without significant cost. What should the general contractor do?
Correct Answer
B) Complete the rebar inspection before proceeding with the pour
Quality control procedures must be followed in sequence. Rebar inspection must occur before concrete placement because once concrete is poured, the rebar cannot be properly inspected or corrected if deficient. The cost of rescheduling is less than the cost of potential structural problems.
Why This Is the Correct Answer
Option B is correct because quality control procedures must be followed in proper sequence, and rebar inspection is a critical step that must occur before concrete placement. Once concrete is poured, it becomes impossible to properly inspect the rebar placement, spacing, and tie connections. The structural integrity of the concrete depends on proper rebar installation, making this inspection non-negotiable. The short-term cost of rescheduling concrete delivery is minimal compared to the potential catastrophic costs of structural failure or having to demolish and rebuild defective work.
Why the Other Options Are Wrong
Option A: Proceed with the pour and inspect the rebar later
This violates fundamental quality control principles and creates serious safety risks. Once concrete hardens around the rebar, inspection becomes impossible, and any defects in rebar placement cannot be corrected without costly demolition.
Option C: Pour the concrete but document the deviation
Simply documenting a deviation does not make it acceptable. This approach still results in uninspected rebar being permanently encased in concrete, creating potential structural deficiencies that documentation cannot remedy.
Option D: Get written approval from the owner to proceed
Owner approval cannot override building code requirements and proper construction sequencing. Even with written approval, the contractor remains liable for structural defects, and the building inspector will still require proper inspections.
Memory Technique
Use the acronym 'FIRST' - Finish Inspections before Reinforcement Solidifies in Time. Always inspect rebar FIRST before concrete pours.
Reference Hint
Florida Building Code Chapter 19 (Concrete) and ACI 318 for reinforcement inspection requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
When preparing a detailed cost estimate for a commercial project, which cost estimating method provides the most accurate results?
Next Question
During a coordination meeting, the HVAC contractor states they need 2 additional days to complete ductwork, which will delay the drywall contractor. The project is already behind schedule. What is the best course of action?