For a $2.5 million commercial project in Florida with moderate complexity and site conditions, what would be an appropriate contingency percentage?
Correct Answer
B) 5-7%
For commercial projects with moderate complexity, a 5-7% contingency is typical. This accounts for unforeseen conditions, minor design changes, and market fluctuations. Higher percentages are used for more complex projects or uncertain conditions.
Why This Is the Correct Answer
For a $2.5 million commercial project with moderate complexity and site conditions, a 5-7% contingency is industry standard. This percentage provides adequate coverage for typical unforeseen conditions like minor soil variations, weather delays, and small design modifications without being excessive. The moderate complexity level indicates standard construction methods and materials, which don't require the higher contingencies needed for complex or high-risk projects. This range balances prudent risk management with competitive bidding practices.
Why the Other Options Are Wrong
Option A: 2-3%
2-3% is too low for a commercial project of this size and would only be appropriate for very simple projects with excellent site conditions and minimal risk factors.
Option C: 10-12%
10-12% is excessive for moderate complexity and would typically be reserved for projects with high complexity, poor site conditions, or significant unknowns.
Option D: 15-20%
15-20% is far too high and would only be justified for extremely complex projects, hazardous conditions, or projects with major uncertainties and risks.
Memory Technique
Use 'SMILE' - Simple (2-3%), Moderate (5-7%), Intense (10-12%), Lethal risk (15%+). The moderate 'M' falls in the middle range of 5-7%.
Reference Hint
Look up contingency guidelines in construction estimating references or Florida Building Code commentary sections on project cost management
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass