During a weekly construction coordination meeting, the electrical subcontractor reports they are 3 days behind schedule on a non-critical path activity with 5 days of total float. What should the general contractor's immediate response be?

Correct Answer

B) Document the delay and continue monitoring since float remains available

Since the activity has 5 days of total float and is only 3 days behind, there is still 2 days of float remaining. The delay does not impact the critical path, so documentation and continued monitoring is appropriate.

Answer Options
A
Immediately accelerate the electrical work at additional cost
B
Document the delay and continue monitoring since float remains available
C
Terminate the electrical subcontractor for poor performance
D
Notify the owner of a project delay

Why This Is the Correct Answer

Option B is correct because the activity still has remaining float (5 days total float - 3 days delay = 2 days remaining). Since this is a non-critical path activity with available float, the delay does not impact the overall project schedule. The appropriate response is to document the delay for tracking purposes and continue monitoring the situation, as no immediate corrective action is required when float remains available.

Why the Other Options Are Wrong

Option A: Immediately accelerate the electrical work at additional cost

Accelerating work immediately would be premature and costly since there are still 2 days of float remaining. This would unnecessarily increase project costs when the delay hasn't yet impacted the critical path or overall project schedule.

Option C: Terminate the electrical subcontractor for poor performance

Terminating a subcontractor for a 3-day delay on a non-critical activity with available float would be an extreme overreaction. This delay doesn't constitute poor performance warranting termination, especially when it doesn't impact the project completion date.

Option D: Notify the owner of a project delay

Notifying the owner of a project delay would be inappropriate since there is no actual project delay. The activity delay is absorbed by the available float, so the overall project schedule remains unchanged.

Memory Technique

Use 'FLOAT = FREEDOM': As long as you have float remaining, you have the freedom to absorb delays without impacting the project completion date.

Reference Hint

Project Management/CPM Scheduling chapter - look for sections on 'Float' or 'Total Float' and 'Critical Path Method'