During a framing inspection, the inspector notes that the work does not match the approved structural plans. What action should the contractor take?
Correct Answer
C) Stop work, correct the framing to match approved plans, and request re-inspection
When construction doesn't match approved plans, work must stop, corrections made to comply with approved plans, and re-inspection requested. This ensures structural integrity and code compliance.
Why This Is the Correct Answer
Option C is correct because when construction doesn't match approved structural plans, the contractor must immediately stop work to prevent further non-compliant construction. The framing must be corrected to match the approved plans since these plans have been reviewed and approved for structural integrity and code compliance. After corrections are made, a re-inspection is required to verify the work now complies with the approved plans before proceeding with construction.
Why the Other Options Are Wrong
Option A: Request the architect to revise the plans to match the construction
Option A is wrong because it reverses the proper process - plans should not be revised to match incorrect construction. The approved plans have already been reviewed for structural integrity and code compliance, so the construction must conform to the plans, not vice versa.
Option B: Continue with the current framing and address it later
Option B is wrong because continuing with non-compliant framing creates serious safety and legal issues. Building on incorrect framing can compromise structural integrity and violate building codes, potentially leading to permit revocation, safety hazards, and costly rework later.
Option D: Apply for a field change order with the building department
Option D is wrong because field change orders are used for approved modifications during construction, not for correcting construction errors. The framing doesn't match approved plans due to construction error, not an intentional design change, so the work must be corrected to match the existing approved plans.
Memory Technique
SRC: Stop, Repair, Call (for re-inspection) - the three steps when construction doesn't match approved plans
Reference Hint
Florida Building Code - Building, Chapter 1 (Scope and Administration) and Chapter 17 (Structural Tests and Special Inspections)
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A property is currently zoned R-1 (Single Family Residential) but the owner wants to build a duplex. What type of approval is needed?
Next Question
You are the general contractor for a new restaurant. The building construction is complete, but the fire department has not yet approved the fire suppression system. Can you obtain a Certificate of Occupancy?