A property is currently zoned R-1 (Single Family Residential) but the owner wants to build a duplex. What type of approval is needed?
Correct Answer
C) Rezoning or zoning variance
Since R-1 zoning typically allows only single-family homes, building a duplex would require either a rezoning to a classification that allows multi-family use or a zoning variance to permit the duplex in the R-1 zone.
Why This Is the Correct Answer
R-1 zoning is specifically designated for single-family residential use only, which means duplexes are not permitted by right in this zone. To build a duplex on R-1 zoned property, the owner must either petition for a rezoning to a multi-family classification (like R-2 or R-3) or apply for a zoning variance that would allow the duplex as an exception to the current zoning restrictions. This is a fundamental zoning compliance issue that requires changing or varying the existing land use regulations.
Why the Other Options Are Wrong
Option A: Building permit variance
A building permit variance relates to construction standards, setbacks, height restrictions, or building code requirements, not to the fundamental land use allowed on the property. The issue here is that the proposed use (duplex) is not permitted in the current zoning classification.
Option B: Conditional use permit
A conditional use permit is used when a proposed use is specifically listed as a conditional or special use in the zoning ordinance for that district. Since duplexes are typically not listed as conditional uses in R-1 zones, this would not be the appropriate approval mechanism.
Option D: Environmental impact permit
An environmental impact permit addresses environmental concerns and potential impacts to natural resources, not zoning compliance issues. This type of permit would only be required if the project had specific environmental impacts regardless of the zoning classification.
Memory Technique
Think 'R-1 = ONE family only' - anything more than one family needs rezoning or variance to change the 'R-1 rule'
Reference Hint
Florida Building Code Chapter 1 - Scope and Administration, and local zoning ordinances section regarding residential classifications and variance procedures
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
During a construction coordination meeting, the electrical subcontractor reports they cannot install conduit until the structural steel is in place, but the steel contractor is delayed by 3 days. What should the general contractor do first?
Next Question
During a framing inspection, the inspector notes that the work does not match the approved structural plans. What action should the contractor take?