During a construction coordination meeting, the electrical subcontractor reports they cannot install conduit until the structural steel is in place, but the steel contractor is delayed by 3 days. What should the general contractor do first?
Correct Answer
B) Analyze the schedule impact and determine if the delay affects the critical path
The first step is to analyze the schedule impact to determine if this delay affects the critical path or if there is available float. This analysis will inform the appropriate response.
Why This Is the Correct Answer
Analyzing the schedule impact and determining if the delay affects the critical path is the proper first step in project management. This analysis provides the factual basis needed to make informed decisions about next steps. Without understanding whether the delay has float or impacts the critical path, any other action would be premature and potentially unnecessary or harmful to project relationships.
Why the Other Options Are Wrong
Option A: Terminate the steel contractor for breach of contract
Terminating the steel contractor would be an extreme overreaction without first understanding the contract terms, reasons for delay, and actual impact on the project. This could lead to legal issues and further project delays.
Option C: Immediately notify the owner of a project delay
Notifying the owner immediately assumes the delay will impact the overall project completion, but without schedule analysis, this may be premature and could damage client relationships unnecessarily if the delay has no impact on the critical path.
Option D: Hire additional workers to make up the lost time
Hiring additional workers is a costly solution that may not address the actual problem and assumes the delay impacts the critical path. This decision should only be made after proper schedule analysis confirms it's necessary.
Memory Technique
Think 'STOP and ANALYZE' - before any major project decision, stop and analyze the schedule impact first
Reference Hint
Project Management chapter - Critical Path Method (CPM) and schedule analysis sections
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass