Under AIA A201, what is the time limit for the architect to respond to a contractor's claim for additional time or money?

Correct Answer

C) 21 days

AIA A201 requires the architect to respond to contractor claims within 21 days of receipt. This timeframe ensures timely resolution of issues and keeps the project moving forward.

Answer Options
A
7 days
B
10 days
C
21 days
D
30 days

Why This Is the Correct Answer

AIA A201 requires the architect to respond to contractor claims within 21 days of receipt. This timeframe ensures timely resolution of issues and keeps the project moving forward.