EstatePass
Contract AdminPermitseasy20% of exam part

During construction, you discover that the structural steel inspection was failed due to improper welding. What is the required next step before proceeding with work?

Correct Answer

B) Correct the deficiency and request a re-inspection

When an inspection fails, the deficiency must be corrected and a re-inspection requested before any subsequent work can proceed. This ensures compliance with approved plans and codes.

Answer Options
A
Continue work and address the issue at final inspection
B
Correct the deficiency and request a re-inspection
C
Submit a variance request to the building department
D
Have the architect approve the existing work

Why This Is the Correct Answer

When any inspection fails, Florida Building Code requires that all deficiencies be corrected before work can continue. The contractor must fix the improper welding, then request a re-inspection from the building department to verify compliance. Only after the re-inspection passes can subsequent construction work proceed. This process ensures structural integrity and code compliance throughout the construction process.

Why the Other Options Are Wrong

Option A: Continue work and address the issue at final inspection

Continuing work after a failed inspection violates Florida Building Code requirements and could result in stop-work orders, fines, and potential safety hazards. All failed inspections must be addressed immediately.

Option C: Submit a variance request to the building department

A variance request is used for seeking approval to deviate from code requirements before construction, not to address failed inspections. Structural welding deficiencies cannot be resolved through variance requests.

Option D: Have the architect approve the existing work

The architect does not have authority to override building code requirements or approve failed inspections. Only the building official can approve inspections after deficiencies are corrected.

Memory Technique

Use 'SFR' - Stop work, Fix deficiency, Request re-inspection. Think 'Safety First Rule' to remember the sequence.

Reference Hint

Florida Building Code Chapter 1, Section 110 - Inspections and Tests

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing