During construction of a commercial building, the contractor failed the rough electrical inspection. How many business days does the contractor typically have to schedule a re-inspection after corrections are made?
Correct Answer
A) 1 business day
Most Florida jurisdictions require re-inspections to be scheduled within 1 business day after failed inspection corrections are completed. This ensures project timelines are maintained while allowing proper correction verification.
Why This Is the Correct Answer
Florida building codes and most local jurisdictions require contractors to schedule re-inspections within 1 business day after completing corrections from a failed inspection. This tight timeline ensures that construction projects maintain momentum while still allowing proper verification of corrected work. The 1-day requirement prevents delays that could cascade through the entire project schedule and helps maintain accountability for prompt correction of code violations.
Why the Other Options Are Wrong
Option B: 3 business days
3 business days would be too long and could cause significant project delays. Florida's building inspection process is designed to keep construction moving efficiently, and a 3-day window would create unnecessary bottlenecks in the construction timeline.
Option C: 5 business days
5 business days represents a full work week delay, which would be excessive for re-inspection scheduling. This extended timeframe could cause major disruptions to construction schedules and is not consistent with Florida's emphasis on efficient inspection processes.
Option D: Same day if corrections are minor
While same-day re-inspection might seem ideal, it's not typically required or guaranteed even for minor corrections. Building inspectors need adequate notice to schedule their routes and workload, making the 1 business day standard more practical and realistic.
Memory Technique
Think 'One and Done' - One business day to get back on track after a failed inspection correction.
Reference Hint
Florida Building Code, Chapter 1 - Administration and Enforcement, Section on Inspections and Re-inspections
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A contractor is estimating concrete for a foundation that measures 120 feet by 80 feet with a thickness of 8 inches. How many cubic yards of concrete are needed?
Next Question
A contractor is evaluating whether to purchase a $85,000 excavator or rent it for $3,500 per month. The excavator will be needed for 18 months and has an expected resale value of $55,000. Which option is more economical?