What is the primary purpose of as-built drawings?
Correct Answer
D) All of the above
As-built drawings serve multiple purposes: they document field changes made during construction, provide accurate records for future maintenance and renovations, and are often required by building departments and owners for project closeout.
Why This Is the Correct Answer
As-built drawings serve all three purposes mentioned in the options, making 'All of the above' the correct comprehensive answer. They are essential construction documents that capture field changes and modifications made during construction that differ from the original plans. These drawings become permanent records that facility managers and future contractors rely on for accurate building information during maintenance, repairs, and renovations. Additionally, most building departments and project owners require as-built drawings as part of the project closeout documentation to ensure compliance and provide official records.
Why the Other Options Are Wrong
Option A: To document changes made during construction
This is partially correct but incomplete - while as-builts do document construction changes, this is only one of their multiple purposes
Option B: To provide a record for future maintenance and renovations
This is partially correct but incomplete - while as-builts do provide maintenance and renovation records, this is only one of their multiple purposes
Option C: To satisfy building department requirements
This is partially correct but incomplete - while as-builts do satisfy building department requirements, this is only one of their multiple purposes
Memory Technique
Remember 'CRM' - Changes (document field changes), Records (for future maintenance), and Municipal requirements (building department compliance)
Reference Hint
Florida Building Code - Chapter 1 (Administration) and project closeout requirements in construction management references
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A project schedule shows Activity X with early start day 15, early finish day 22, late start day 18, and late finish day 25. What is the total float for Activity X?