Who is typically responsible for maintaining and updating as-built drawings during construction?
Correct Answer
C) The general contractor with input from all trades
The general contractor is typically responsible for maintaining as-built drawings with input from all trades and subcontractors. This ensures comprehensive and accurate documentation of all construction changes.
Why This Is the Correct Answer
The general contractor serves as the central coordinator for all construction activities and has the overall responsibility for project documentation. As-built drawings require input from all trades since each subcontractor makes changes and modifications within their scope of work. The GC is best positioned to collect, coordinate, and maintain these updates from all parties to ensure comprehensive and accurate documentation. This responsibility aligns with the GC's role as the primary contractor accountable to the owner for complete project delivery.
Why the Other Options Are Wrong
Option A: The architect only
The architect alone cannot maintain as-built drawings because they are not present on-site daily and do not have direct knowledge of all field changes made by various trades during construction.
Option B: Each individual subcontractor
Individual subcontractors only have knowledge of their specific trade work and cannot coordinate or maintain the complete set of as-built drawings that encompasses all building systems and trades.
Option D: The owner's representative
The owner's representative typically does not have the technical expertise or detailed knowledge of construction methods and changes to accurately maintain as-built drawings throughout the construction process.
Memory Technique
Think 'GC Gathers Changes' - the General Contractor Gathers all Changes from every trade to maintain accurate as-built documentation.
Reference Hint
Florida Building Code, Chapter 1 - Administration and Enforcement, or AIA Contract Documents A201 - General Conditions regarding contractor responsibilities
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
During a weekly construction coordination meeting, multiple trades report conflicts with the HVAC ductwork installation. What documentation should the general contractor require?
Next Question
A change order increases the contract value by $45,000 and extends the completion date by 12 days. The original contract was $780,000 with a 120-day duration. What is the new contract value and duration?