A LEED project requires that 75% of construction waste be diverted from landfills. If a project generates 480 tons of waste and recycles 340 tons, does it meet this requirement?
Correct Answer
B) No, it only achieves 70.8% diversion
Waste diversion rate = (340 tons recycled / 480 tons total) × 100 = 70.8%. This falls short of the required 75% diversion rate for LEED compliance.
Why This Is the Correct Answer
Option B is correct because it accurately calculates the waste diversion rate as 70.8% and correctly identifies that this does not meet the LEED requirement. The calculation shows 340 tons recycled ÷ 480 tons total × 100 = 70.8%. Since 70.8% is less than the required 75%, the project fails to meet the LEED standard. The answer correctly states both the percentage achieved and that it falls short of compliance.
Why the Other Options Are Wrong
Option A: Yes, it achieves 70.8% diversion
Option A calculates the correct percentage (70.8%) but incorrectly concludes that the project meets the requirement. Since 70.8% is less than the required 75%, the project does NOT meet LEED compliance standards.
Option C: Yes, it achieves 75.8% diversion
Option C provides an incorrect calculation of 75.8% and wrongly concludes the project meets requirements. The actual diversion rate is 70.8%, not 75.8%, making both the calculation and conclusion incorrect.
Option D: No, it only achieves 68.2% diversion
Option D has an incorrect calculation showing 68.2% instead of the actual 70.8%. While it correctly identifies that the project doesn't meet requirements, the mathematical error makes this answer wrong.
Memory Technique
Remember 'LEED Loves 75' - LEED projects typically require 75% waste diversion. Always check if your calculated percentage meets or exceeds this threshold.
Reference Hint
Look up LEED requirements and sustainable construction practices in the Green Building/Environmental chapter of your contractor reference manual
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A general contractor is building a 3,500 square foot commercial office building. The building permit fee is $2.50 per square foot for the first 2,000 sq ft and $1.75 per square foot for each additional square foot. What is the total permit fee?
Next Question
What constitutes substantial completion under most construction contracts?