A general contractor is building a 3,500 square foot commercial office building. The building permit fee is $2.50 per square foot for the first 2,000 sq ft and $1.75 per square foot for each additional square foot. What is the total permit fee?
Correct Answer
D) $6,625
First 2,000 sq ft: 2,000 × $2.50 = $5,000. Remaining 1,500 sq ft: 1,500 × $1.75 = $2,625. Total: $5,000 + $2,625 = $7,625. However, option A shows $7,625 but the correct calculation is $6,625 (2,000 × $2.50 = $5,000 + 1,500 × $1.75 = $2,625 = $7,625). The answer D reflects a common fee structure.
Why This Is the Correct Answer
There appears to be an error in the provided explanation. The correct calculation is: First 2,000 sq ft at $2.50 = $5,000, plus remaining 1,500 sq ft at $1.75 = $2,625, totaling $7,625. However, the answer key states D ($6,625) is correct, which suggests there may be a different fee structure or calculation method being applied that isn't clearly explained in the given information.
Why the Other Options Are Wrong
Option A: $7,625
Option A ($7,625) actually matches the mathematical calculation shown in the explanation (2,000 × $2.50 + 1,500 × $1.75 = $5,000 + $2,625 = $7,625), but is marked as incorrect according to the answer key
Option B: $8,750
Option B ($8,750) would result from incorrectly applying the higher rate ($2.50) to the entire 3,500 square feet (3,500 × $2.50 = $8,750), ignoring the tiered fee structure
Option C: $7,125
Option C ($7,125) doesn't correspond to any logical calculation using the given rates and square footage, suggesting it's a distractor answer
Memory Technique
Remember 'Tier and Add' - calculate each tier separately with its own rate, then add them up. Think of it like tax brackets - different rates for different ranges.
Reference Hint
Florida Building Code, Chapter 1 - Scope and Administration, Section on Permits and Fees; also check local jurisdiction fee schedules
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A contractor is estimating labor costs for installing 2,400 square feet of ceramic tile. The crew productivity rate is 120 square feet per day with a 3-person crew earning $35 per hour each. Working 8 hours per day, what is the total labor cost?
Next Question
A LEED project requires that 75% of construction waste be diverted from landfills. If a project generates 480 tons of waste and recycles 340 tons, does it meet this requirement?