A contractor must obtain a Certificate of Occupancy before the building can be occupied. Which entity typically issues the CO?
Correct Answer
B) Local building department or authority having jurisdiction
The Certificate of Occupancy is issued by the local building department or the authority having jurisdiction after all required inspections are completed and the building is deemed safe for occupancy according to the approved plans and applicable codes.
Why This Is the Correct Answer
The local building department or authority having jurisdiction (AHJ) is responsible for issuing Certificates of Occupancy because they are the entities that conduct the required inspections throughout the construction process. They verify that the building complies with local building codes, zoning requirements, and the approved construction plans. Once all final inspections are passed and any deficiencies are corrected, the local building department has the authority to certify that the building is safe for occupancy. This is a fundamental local government function that ensures public safety at the community level.
Why the Other Options Are Wrong
Option A: Florida Department of Business and Professional Regulation
The Florida Department of Business and Professional Regulation (DBPR) regulates contractor licensing and professional standards, but does not issue Certificates of Occupancy for individual buildings.
Option C: Florida Department of Environmental Protection
The Florida Department of Environmental Protection handles environmental regulations and permits, but does not issue Certificates of Occupancy for building occupancy.
Option D: Regional planning council
Regional planning councils focus on long-term regional development planning and coordination, but do not have authority to issue Certificates of Occupancy for individual buildings.
Memory Technique
LOCAL CO: 'Local Officials Check All Living Occupancy Certificates Only' - emphasizes that COs are always issued by local authorities, not state agencies.
Reference Hint
Florida Building Code, Chapter 1 - Scope and Administration, Section 110 Certificate of Occupancy
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A roofing contractor's productivity decreases from 25 squares per day to 20 squares per day due to hot weather conditions. If the normal crew cost is $2,000 per day, what is the cost per square under the reduced productivity?
Next Question
In CPM scheduling, the critical path is defined as: