A client wants to build a restaurant in a strip mall zoned for general commercial use. The local zoning code requires a special use permit for restaurants. What is required?
Correct Answer
C) Special use permit from the planning commission
Even in commercial zones, some uses like restaurants may require special use permits due to traffic, parking, or other impacts. This must be obtained before building permits.
Why This Is the Correct Answer
A special use permit is required because the zoning code specifically mandates it for restaurants, even in commercial zones. Special use permits are conditional approvals that allow certain uses in zones where they may have unique impacts on traffic, parking, noise, or other community concerns. The planning commission reviews these applications to ensure the proposed use is compatible with the surrounding area and meets specific conditions. This permit must be obtained before any building permits can be issued.
Why the Other Options Are Wrong
Option A: No additional approvals needed
This is incorrect because the question clearly states that the local zoning code requires a special use permit for restaurants, so additional approvals beyond basic zoning compliance are definitely needed.
Option B: Building permit only
A building permit alone is insufficient because it cannot be issued until all required zoning approvals, including the special use permit, are obtained first. The building permit addresses construction compliance, not land use authorization.
Option D: Variance from zoning requirements
A variance is not needed because restaurants are allowed in commercial zones with a special use permit. Variances are only required when seeking relief from zoning requirements that would otherwise prohibit the use entirely.
Memory Technique
Think 'SPECIAL situations need SPECIAL permits' - restaurants, gas stations, and other high-impact businesses often need special use permits even in zones where they're generally allowed.
Reference Hint
Florida Building Code Chapter 1 - Scope and Administration, and local zoning ordinance sections on special use permits and conditional uses
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
According to OSHA requirements, what must be documented during safety toolbox talks?
Next Question
A subcontractor performs work on a private project but never receives a Notice to Owner form from the general contractor. Under Florida lien law, what is the subcontractor's lien rights status?