During contract closeout, the contractor discovers that $8,000 in retainage is being withheld for warranty items that were completed satisfactorily. The owner claims the items may fail during the warranty period. What is the contractor's best course of action?
Correct Answer
B) Request a warranty bond in lieu of cash retention
Requesting a warranty bond allows the contractor to receive the retained funds while still providing the owner security for warranty obligations. This is a common and reasonable solution during closeout.
Why This Is the Correct Answer
Requesting a warranty bond in lieu of cash retention is the best solution because it provides the owner with financial security for warranty obligations while allowing the contractor to receive their retained funds immediately. This approach balances both parties' interests - the owner gets protection against potential warranty claims, and the contractor gets their money without having to wait through the entire warranty period. Warranty bonds are a standard industry practice and are typically accepted by owners as adequate security.
Why the Other Options Are Wrong
Option A: Accept the retention since warranty coverage is required
Simply accepting the retention is not the best course of action because it unnecessarily ties up the contractor's funds when there are better alternatives available that protect both parties' interests.
Option C: Agree to extended retention for the specific warranty items only
Agreeing to extended retention for specific warranty items still leaves the contractor's money tied up unnecessarily when a warranty bond could provide the same protection to the owner while freeing up the contractor's cash flow.
Option D: Demand immediate release since the work was completed satisfactorily
Demanding immediate release ignores the owner's legitimate concern about warranty obligations and doesn't offer any alternative security, which could damage the business relationship and may not be legally enforceable.
Memory Technique
Think 'Bond = Best of Both' - warranty bonds serve both parties' interests better than cash retention
Reference Hint
Florida Building Code Chapter 1, Section 107 - Submittal Documents, and contract administration sections dealing with retainage and warranty provisions
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
What is the main difference between a contingency and an allowance in construction estimating?
Next Question
In a Guaranteed Maximum Price (GMP) contract with shared savings, the GMP is $750,000 with actual costs of $720,000. If savings are split 50/50, how much does the contractor receive?