According to Florida Statute Chapter 713, within how many days must a contractor serve a Notice to Owner after first providing labor or materials to the project?
Correct Answer
B) 45 days
Florida Statute Chapter 713 requires that a Notice to Owner be served within 45 days after the lienor first provides labor, services, or materials to the improvement. This notice preserves the right to claim a construction lien.
Why This Is the Correct Answer
Florida Statute Chapter 713.06 specifically mandates that a Notice to Owner must be served within 45 days after the lienor first furnishes labor, services, or materials to the improvement. This 45-day requirement is a critical deadline that preserves a contractor's or subcontractor's right to file a construction lien. Failure to serve this notice within the statutory timeframe can result in the complete loss of lien rights, making this one of the most important compliance requirements in Florida construction law.
Why the Other Options Are Wrong
Option A: 30 days
30 days is too short and does not align with Florida Statute Chapter 713 requirements for Notice to Owner service.
Option C: 60 days
60 days exceeds the statutory requirement and would be considered late service, potentially invalidating lien rights.
Option D: 90 days
90 days is far beyond the statutory deadline and would definitely result in loss of lien rights under Florida law.
Memory Technique
Think '45 = Forty-Five days to File' - the alliteration helps remember that you have 45 days to file your Notice to Owner to preserve lien rights.
Reference Hint
Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.06 regarding Notice to Owner requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A contractor needs 250 cubic yards of concrete for a foundation. The concrete costs $120 per cubic yard delivered, and there is typically 3% waste. What is the total material cost including waste?
Next Question
A Registered Building Contractor in Florida wants to take on a project valued at $350,000. What action must they take?