A construction site fire extinguisher inspection reveals the pressure gauge is in the red zone. What immediate action should be taken?
Correct Answer
B) Remove from service and replace immediately
A fire extinguisher with a pressure gauge in the red zone is not properly pressurized and will not function effectively in an emergency. It must be removed from service immediately and replaced with a properly functioning unit.
Why This Is the Correct Answer
A fire extinguisher with a pressure gauge in the red zone indicates the unit is either over-pressurized or under-pressurized, both of which render it unreliable or non-functional in an emergency. OSHA regulations and fire safety codes require immediate removal from service of any defective fire safety equipment. The extinguisher must be replaced with a properly functioning unit to maintain fire protection on the construction site. Continuing to rely on a faulty extinguisher puts workers and property at serious risk.
Why the Other Options Are Wrong
Option A: Continue using until the next scheduled maintenance
Testing by discharge is dangerous and wasteful - if the extinguisher is over-pressurized it could cause injury, and if under-pressurized the test confirms it's defective while also depleting any remaining contents. This approach provides no benefit and creates additional safety risks.
Option D: Test the extinguisher by discharging a small amount
This is extremely dangerous and violates OSHA safety requirements. A malfunctioning fire extinguisher provides no fire protection and creates a false sense of security that could lead to catastrophic consequences during an actual fire emergency.
Memory Technique
RED ZONE = REMOVE - both start with 'R' and red means stop/danger, so stop using it immediately
Reference Hint
OSHA Construction Standards 29 CFR 1926.150 - Fire Protection, and NFPA 10 Standard for Portable Fire Extinguishers
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass