EstatePass
Contract AdminContractsmedium40% of exam part

In a cost-plus-fee contract with a 12% fee, if the actual project costs are $420,000 and there was a $15,000 cost overrun due to owner changes, what is the total amount due to the contractor?

Correct Answer

C) $487,200

Total costs including overrun: $420,000 + $15,000 = $435,000. Fee: $435,000 × 12% = $52,200. Total due: $435,000 + $52,200 = $487,200.

Answer Options
A
$470,400
B
$485,400
C
$487,200
D
$472,200

Why This Is the Correct Answer

In a cost-plus-fee contract, the contractor is reimbursed for all legitimate project costs plus a predetermined fee percentage. The total project costs include both the original costs ($420,000) and any approved cost overruns ($15,000), totaling $435,000. The 12% fee is calculated on the entire cost basis of $435,000, resulting in a fee of $52,200. The total amount due is the sum of all costs plus the fee: $435,000 + $52,200 = $487,200.

Why the Other Options Are Wrong

Option A: $470,400

This answer incorrectly calculates the fee on only the original project costs ($420,000 × 12% = $50,400) and adds it to the total costs including overrun ($420,000 + $15,000 + $50,400 = $485,400), but the fee should be calculated on the total costs including overruns.

Option B: $485,400

This answer appears to calculate the fee on the original costs only ($420,000 × 12% = $50,400) and then adds it to the total costs ($420,000 + $15,000 + $50,400 = $485,400), which is the same error as option A but presented as a different value.

Option D: $472,200

This answer incorrectly calculates the fee on only the original project costs ($420,000 × 12% = $50,400) instead of on the total costs including overruns, resulting in $420,000 + $15,000 + $50,400 = $485,400, but shows as $472,200 which suggests a calculation error.

Memory Technique

Remember 'TOTAL before FEE' - always calculate the fee percentage on the total project costs (including overruns), not just the original estimate.

Reference Hint

Look up contract types and payment methods in Chapter 4 (Project Management) or Chapter 6 (Construction Contracts) of your Florida contractor exam reference guide.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing